We insulated 11 steel container modules in an Estonian factory that will be assembled into a mobile shooting range for a Finnish customer. The floors, walls and ceilings of the modules were insulated with closed-cell PUR foam Heatlok Shield.

Client's request

The shooting range is designed for use in various locations, with the modules being transported from one site to another. The client wanted the best possible insulation for Finland's cold climate, which does not lose its thermal performance during transport.

The module manufacturer wanted the best quality and an installer with extensive experience. The foam layer had to be applied with an accuracy of half a centimetre because the modules were already painted and excess foam could not be cut off.

Steel module of the shooting range before insulation, edges covered with protective paper
The module steel frame before installing closed-cell PUR foam

Why Heatlok Shield

  • Bonds strongly to steel. The foam adheres to the steel structure over its entire surface and retains its thermal insulation even when the module is transported from one place to another.
  • Best thermal insulation in our range. Heatlok Shield has a lambda value of 0.027 W/mK, so the same result can be achieved with a thinner layer.
  • Seamless layer. The foam also fills corners and the gaps between profiles so that no thermal bridges are formed.
  • Does not absorb moisture. Closed-cell foam protects steel surfaces from condensation.

Read more about the difference between closed-cell and open-cell foam in the article open- or closed-cell PUR foam.

Module wall after foaming, closed-cell PUR foam Heatlok Shield

How the modules were insulated

The thickness of the layer in the floor, walls and ceiling varied from 50 to 200 mm. We apply closed-cell foam in layers, up to 50 mm at a time. The edges and surroundings of the modules were covered with protective paper and film before foaming. At the request of the factory, we worked with a flexible schedule and the work lasted a month and a half in total.

End and side walls of the module after insulation with Heatlok Shield foam

Briefly

  • Project: mobile shooting range, 11 steel container modules
  • Insulated: floor, walls and ceiling
  • Foam: Heatlok Shield, closed-cell PUR foam
  • Layer thickness: 50 to 200 mm
  • Accuracy: within half a centimetre, without post-processing
  • Duration of work: a month and a half, according to the factory schedule

We also insulate other modular and container buildings, industrial buildings and hangars. Find out more on the page insulation of industrial buildings and hangars or read how we do shipping container insulation with PUR foam. You can get an idea of the price on the price page. For an exact price, send us the area and layer thickness and we will prepare a personal quote for you.